Baton Rouge, Louisiana
Pipe Details
- 2-inch (50.8-mm) carbon steel pipe, transporting butene and hexene, experienced corrosion under insulation
- 2 locations at a double elbow required repair
- Design Pressure: 285 psi (2 MPa)
- Operating Pressure: 100 psi (0.7 MPa)
- Design Temperature: 100˚F (38˚C)
Summary
- 2-inch (50.8-mm) carbon steel pipe, transporting butene and hexene, experienced CUI
- After 5 years of service, the repair was as good as new
- The owner was confident to continue operations with the composite repair for 2 more years
- ThermoWrap was applied to the original CUI damage to repair 2 locations at a double elbow
- 2 trained technicians repaired the damage in a matter of hours
Benefits
CSNRI delivered a fast, reliable and extremely cost-effective solution to a potentially costly and unsafe issue for the chemical plant. The ThermoWrap composite system enabled safe, uninterrupted service for 5 years and was deemed serviceable by the plant owner for another 2 years. If the next turnaround has not been scheduled at that time, the integrity of the repair will be reassessed to determine if it is suitable for continued safe service.
Most composite repairs resolve integrity issues and then simply become another part of the safely functioning piping system. Once repairs are made in plants and refineries, owners normally make plans to replace the damaged sections during a scheduled turnaround, so the technicians who carried out the repair may never see how the repair has performed in service when it reaches end of life. Occasionally, however, there is an opportunity to examine a repair that has been in service. On these rare occasions, it provides a great opportunity to assess just how well the composite has performed over time. Five years after applying the ThermoWrap composite system to repair corrosion under insulation (CUI) on two elbows on a 2-inch (50.8-mm) carbon steel line transporting butene and hexene at a chemical plant in Baton Rouge, Louisiana, plant engineers found themselves with the need to review the possibilities to keep the repairs operating. Although plans had been made to replace the repaired piping during a turnaround, because the date for the turnaround was repeatedly postponed, the section of repaired pipe was still in service. To make sure there were no safety issues, an inspection team at the plant was examining the repair to evaluate the line. A visual examination showed that over the span of 5 years of demanding service, the system had undergone no degradation. The repair was pristine, and the integrity of the asset was unaffected.




