Water Main Structural Strengthening
DETAIL
- 40 million litres of potable water lost, and 140 residents displaced after water line rupture.
- Fyfe provided internal, fully structural trenchless rehabilitation solution using Carbon Fiber Reinforced Polymer (CFRP) to strengthen the four critical pipe segments.
- Durable, long‑term asset renewal solution delivered.
- Risk of repeat failures on a vital transmission main
- Sensitive to public's impact in response to the August pipeline failure
- Constraints on excavation, given the pipe’s location beneath major arterial roads
- The need to minimise traffic disruption and community impact
- Challenging winter conditions, with repair works required during Montreal’s harsh cold season

- Internal access via existing manways and valve chambers, avoiding surface excavation
- A unidirectional CFRP system installed longitudinally and circumferentially to address governing limit states
- A watertight glass‑fiber layer to protect the composite and enhance durability
- A phased installation approach to manage logistics and service continuity
- Extreme winter weather, including record snowfall and sustained sub‑zero temperatures
- Highly variable internal pipe temperatures, particularly during Phase 1 where pipe segments were widely spaced
- Temperature‑sensitive curing requirements, critical to achieving required CFRP material properties
- Restricted access and long distances inside the pipeline, complicating heating, ventilation, and logistics
- A newly trained installation crew, requiring enhanced quality control and supervision
- Designing and implementing temporary heated and insulated work enclosures
- Deploying multiple electric heater banks, baffles, and bulkheads to control zonal temperatures
- Continuous temperature and humidity monitoring using data loggers
- Adjusting work sequencing o prioritise colder, more remote pipe sections first
- Increasing field inspection frequency, including daily intermediate layer inspections
- Conducting daily witness sample testing to verify material properties and curing performance
- Providing ongoing technical support from Fyfe’s CFRP specialists throughout installation