Fyfe System Projects and Case Studies

Fyfe®'s Tyfo® FRP systems - Advanced composites for structural strengthening - have been used for the rehabilitation of a range of applications covering many industries. Here you will find details of many of our projects supported by detailed case studies. 

Larnaca Sewage Treatment Plant Tank Rehabilitation

The Larnaca Sewage and Drainage Board was created in the later 1970s following heavy rainfall which caused destructive floods in the region. The system at the time needed to be upgraded due to the influx of development in the region, and when the flood occurred the town Major took the decision to place a focus on the provision of improved sewage and draining services.

100-Year-Old Penstock Given New Lease of Life by Tyfo System

100-Year-Old Penstock Given New Lease of Life by Tyfo System. The Eagle River Generation Station is a hydroelectric generating station located near the Town of Dryden, Ontario, Canada. Eagle River, in addition to McKenzie and Wainwright stations, provide a combined 3.9 MW of energy to the local power grid.

Intermountain Power Plant

Intermountain Power (IMP) has been a user of carbon fiber-reinforced polymer (CFRP) for strengthening of their circulating cooling water systems (CW) for over 10 years.

Beacon Street Pipeline Rehabilitation

In 1870, a new 48-inch cast iron water main was installed in the Brookline area of Boston to provide additional potable water supply to residents. Almost 150 years later, this pipeline today now supplies over 21 million gallons (or approximately 15 percent of the total daily water supply) per day to the region.

66-Inch I-25 Steel Pipeline Rehabilitation

Denver Water experienced a catastrophic failure in February 2008 when a section of a 66-inch steel pipeline that conveys water to the northern part of the City failed under I-25 due to a sudden surge from a pump failure.

A120-Inch Dominion Pipe Rehabilitation

The Tyfo® system was used as a liner to provide corrosion protection and nominal hoop tension strength on a 120-inch diameter steel pipe at a nuclear power plant in Yorktown, Virginia.
The 120-inch diameter steel pipe at this power plant was severely rusted due to the surrounding corrosive environment. A repair solution was needed that could not only withstand the harsh environment but could also be installed with minimal shut down time at the plant.

US Army Corp of Engineers/Zoar Levee 36-Inch Box Culvert Joint Strengthening

Site preparation and bypass pumping of the creek water and storm flows was provided by the prime contractor, Massillon Stone Company, which utilized an 8-inch dry prime pump and 8-inch irrigation piping. The pumping system had to overcome a 150 vf levee wall to force the water from the base of the levee wall to the top of the levee for discharge. The trenchless repair was performed by entering the line and hand applying the Tyfo® Fibrwrap® CFRP system.

Nuclear Power Plant Pipe Rehabilitation

The fiber wrap design was standalone throughout the straight pipe segments and designed as a composite section at the bends and at the supports; this allowed for the remaining steel section to provide the stiffness required in resisting thrust forces at those locations. Once the fiber installation was completed, compression rings were applied at the fiber terminations for improved detailing and to prevent shear slipping due to longitudinal forces.

Fibrwrap Helps Strengthen a Las Vegas Power Plant

The scope of work included conducting the internal surface preparation by media blasting and internal installation of the Tyfo® carbon fiber material on 440ft of 36-inch diameter steel pipe and 310 ft of 32-inch diameter steel pipe including numerous eight tees, five 90° elbows, two reducers and one dead head.

Refinery Flare Line Repair

Fyfe/Fibrwrap worked closely with the client to develop a solution that would both satisfy the client’s process safety requirements, and be cost effective to install. Ultimately, a high temperature Tyfo® system was proposed that met the client’s needs and specifications.

SJRA – Lake Houston Pump Station #2 Effluent Pipe Lines Rehabilitation

The scope of work included strengthening segments on each of the three effluent pipe lines, including conducting the required surface preparation, end detailing, fiber installation, finish coat installation and conducting all the required quality control measures. The pipe length of each repaired section was 13, 18 and 27 lineal feet.

66-Inch, I-270 PCCP Pipeline Rehabilitation

Fibrwrap Construction installed the Tyfo® SCH-41 2X system (unidirectional carbon fiber) both in the circumferential and longitudinal directions. The materials were designed as a standalone repair to withstand operating and transient pressures as well as gravity loads.

Water Reservoir Rehabilitated with Fyfe's Tyfo Systems

A non-ductile concrete tank built on a hillside in Southern California in the 1940s was identified as requiring a seismic upgrade. The reservoir provides water to more than 3,000 homes and has the capacity to supply 10 million gallons of water per day.

Buckled and Deformed Penstock Rehabilitation

Power output dropped at the Mississippi River Power Corp.’s 4.6-MW Brian J. Gallagher Generating Station, on the Mississippi River in Ontario, Canada. The buckled and deformed penstock required rehabilitation.